  1. Capital projects must receive preliminary approval from a Dean, or the Vice President for Administration and Finance prior to being submitted to the Office of Facilities.
  2. Based on an initial plan, The Office of Facilities will develop and estimated cost and preliminary drawings for the project.
  3. Facilities will discuss the initial plan and estimated cost with the requestor. After initial authorization, and verification of an approved account number, Facilities will provide final plans specifications and a final estimated cost based upon any revisions that have been made.
  4. Upon completion of final plans, drawings and specification, Facilities will prepare timelines for the project and invite a group of Contractors to bid the specific project.
  5. The Project Manager throughout the duration of the project handles all Contractor interactions.

 